headbg headbg
 
     
CAPRI letter to Tewkesbury BC

19th February 2009

 

 

Dear Mr Rider,

 

NATIONALGRID plc – Proposed construction of PRI and associated works;

Application Number 08/01665/FUL

 

Thank you for your letter of 3rd February and for kindly supplying us with copies of the documents submitted to you by National Grid plc (NG).

 

In your letter you invited CAPRI to comment on the application: we believe that there are seven substantive issues raised by the application and our comments are set out below.

 

1.         THE APPLICANT

NG is a public limited company - one of very many - and as such enjoys no special status in planning matters and thus deserves no special consideration in respect of any planning applications which it may submit.

 

CAPRI has learned from experience that NG makes claims which need to be treated with considerable caution. NG has issued for public consultation documents which are inaccurate and misleading; for example, Fact Sheet 7 suggests that NG consulted local authorities and CAPRI before choosing the two short listed sites mentioned in Paragraph 4 below. CAPRI was not consulted; its representatives did no more than attend meetings at which NG reported on the progress made with the search mentioned in that paragraph.

 

Similarly, Factsheet 7 contains an artist’s impression of the proposed PRI 1 year and 10 years after construction. Neither impression gives any indication whatever of the 12 x 8.5m high vent stacks and they therefore contradict Drawing H132/BH/01/01/4629/954 A which shows clearly that the vent stacks will be visible for many years after the PRI is completed.

 

2.         THE APPLICATION SITE (the Site)

The choice of the Site arises as a direct result of the history of gas installations in this area . As far as CAPRI is aware, major gas transmission works began in this area after planning permission was granted in October 1969 to construct an underground control valve installation on the site of the present Above Ground Installation (AGI). We do not know why this site was selected and there is no evidence that such selection was part of a strategy approved after careful research: we suspect that chance played a significant part in the selection process. Because the majority of the proposed works were to be underground, the planning authority granted permission doubtless because there was no known good reason to do otherwise.

 

Subsequently NG applied to enlarge the original site and to construct what is now the present AGI: again, because of the then existing installation, the Planning Authority had no overwhelming reason to refuse the application and granted permission in April 2000. Subsequently NG formulated plans for the transmission of natural gas from Milford Haven to connect to the National Transmission System (NTS) and it concluded that the proper location for the connection was immediately proximate to the Tirley AGI where it would need to build a Pressure Reduction Installation (PRI). NG therefore submitted a planning application to Forest of Dean District Council in March 2006 seeking permission to construct a PRI in that location; the Principal Planning Officer of the Council recommended that the application be approved but CAPRI persuaded the members of the Development Committee to reject that recommendation and refuse permission because of the serious adverse visual impact of the installation and the conflict with adopted county and district policies on severely restricting development in the countryside.

 

NG appealed against that refusal of permission and their appeal failed. The Inspectors agreed with CAPRI that the appeal site was not a reasonable one for an industrial installation in a tranquil rural area and, furthermore, expressed the view that NG had failed to search adequately for possible alternative sites. After publication of the appeal decision, NG commenced a search for alternative sites within the 10km radius mentioned by the Inspectors; NG took nearly 12 months to complete that search, produced a list of 23 “representative areas” for further consideration and concluded that of those the two most appropriate were an enlarged area of the former appeal site and the Site, both of which happen to be immediately proximate to the existing pipelines. It is that proximity and the consequent saving in cost which resulted in that choice of Site for the present application. Apart from those two factors, the Site has no merit whatever as a site for a substantial industrial installation. The history mentioned above demonstrates how a small, underground, unobtrusive installation can become a much larger AGI and then – possibly – become an even larger PRI. This highlights the risk inherent in permitting the present application because if permission is granted it would approve the principle of siting a substantial industrial installation in this area and - because the principle had thus been established - it would be very difficult for a planning authority to resist future requests for expansion or even new installations.

 

3.         PLANNING POLICIES

You will be very familiar with the national and local policies designed to protect the countryside from development. I will not weary you with quoting from them but I would mention:

  • PPS 7 Paragraph 1(iv) which states that new development in the open countryside "should be strictly controlled; the Government's overall aim is to protect the countryside for the sake of its intrinsic character and beauty, the diversity of its landscapes, heritage and wildlife"
  • Policy LND4 which states that "in considering proposals for development in rural areas - regard will be given to the need to protect the character and appearance of the rural landscape".

 

The proposed development of the Site cannot possibly comply with those Policies.

 

4.         ALTERNATIVE SITES

Notwithstanding the history of NG's developments in this location, the issue of alternative sites for the PRI has been handled very badly by NG. At the time of the previous appeal, NG asserted that 14 alternative locations for the PRI had been considered all of which lay within 1km of the existing AGI and very proximate to the existing gas pipelines. NG asserted that the proposed PRI had to be located very close to the existing AGI but this assertion was challenged at the Inquiry and NG was forced to admit that the assertion was false and that the efficiency of the PRI would not in any way be impaired if it were located anywhere within a radius of 10km of the AGI. Before the present application was submitted, representatives of NG, three local planning authorities and CAPRI visited the "representative areas" mentioned in Paragraph 2 above; the process used by NG which resulted in the selection of those "areas" was almost incomprehensible because some of the areas were on open and elevated ground and thus patently unsuitable as a site for an industrial installation. However at least one of those areas would lend itself to development of the type proposed because of its isolation, the existence of a natural depression in the ground and substantial adjacent woodland.

 

At the Public Inquiry, CAPRI advocated that the PRI should not be constructed on undeveloped land anywhere within this 10km radius but at the existing NG site at Wormington, an important hub within the existing NTS and where there is adequate room to accommodate the PRI without any significant expansion of the existing installation. In the Inspectors' report after the Inquiry, they concluded that it was technically feasible to locate the PRI at Wormington but NG had claimed that the additional cost of laying the new 48” pipe from Tirley to Wormington would be in the order of £57m and that such additional cost was not justified. In view of the Inspectors' conclusion, the only remaining argument against the Wormington site is the matter of cost, and cost is not  - and never has been - a planning consideration. It seems to us that in dealing with industrial installations of this size and importance it makes more sense to group them together in one location – for reasons of safety, security and efficiency – than to have them scattered over a wide area. The total cost  of providing the pipeline from Milford Haven to Wormington with the attendant installations is believed to be approaching £1bn and £57m is a very small proportion of that overall cost.

 

5.         APPEARANCE

The application which became the subject of the appeal envisaged an industrial installation contained within a rectangular, engineered embankment with an average height of 3.5m, topped by deciduous trees and shrubs; the height of those new trees projected by NG was described by the Inspectors as being ‘significantly higher than even the optimum growth rates would achieve’. The design was pedestrian, unimaginative and inadequate and the Inspectors said that the “quality of the landscaping … would fall far short of what should be expected from a statutory undertaker”.

 

The present application proposes yet again the creation of embankments – this time of an average 5m in height - around another rectangular site, together with an inadequate plan for planting deciduous trees and shrubs. Rectangular embankments are an unnatural feature in a rural landscape and the proposal is to plant only deciduous trees with the result that for six months of the year the trees could not provide effective screening of the new installation. In fact, the new landscaping proposals are little different from the previous proposals and continue to fall far short of what would be needed to integrate the PRI into the landscape effectively.

 

We have mentioned in paragraph 1 above the appearance of the 12 vent stacks each 8.5 m high but the plans submitted show that NG proposes in addition to erect 20 maintenance lighting columns, each 8m high, the purpose of which is to illuminate the entire site at night when maintenance is required. The columns themselves will be visible for many years but their illumination at night is bound to create significant light pollution.

 

6.         ACCESS

We believe that there will be substantial problems arising from access to the Site from the B4213 particularly during construction but also thereafter. The B4213 is a heavily used, straight and fast road with hidden dips which can seriously impair visibility.

 

7.         SECURITY

The issue of security is a matter of major concern to local residents. The PRI inevitably becomes a potential terrorist target as soon as construction is completed. There are occupied dwelling within 350m of the centre of the Site which is designed to be unmanned and will be protected only by a 2.4m high security fence with an internal electrified fence 4m high. The fences of themselves would present little difficulty to a determined terrorist who could use explosives to gain entry. We understand that within the site there will be electronic detection devices and security lighting which will transfer data to NG's control centre which would alert the Gloucestershire Constabulary whose officers would then travel to the PRI and take whatever action appeared appropriate. We understand that the police response would probably be either by a single officer in a police car or an armed response team. The time taken between receipt of the alert and arrival at the PRI would depend on various factors including the availability of resources, weather conditions and – very relevant to this area - flooding. If a terrorist did force an entry, explosives could be used firstly to fracture pipes or other parts of the installation and then ignite the escaping gas to cause an explosion which could devastate a significant area. Local residents therefore run the risks of losing their homes -  a risk which is uninsurable -  and also their lives.

 

8.         CONCLUSION

It is well established that all planning applications should be considered on their merits and this application has no merit whatever. The Site is not suitable for the construction of an industrial installation and conflicts with approved national and local planning policies. No justification whatever on planning grounds has been provided by NG for the selection of the Site as suitable for the construction of a significant industrial installation in an undeveloped, tranquil area of open countryside. NG has selected the Site as a matter of economic convenience because of proximity to the existing pipelines and NG has never considered any alternative that was not proximate to those pipelines. That primary consideration made the search for alternatives mentioned in Paragraph 4 above a pointless exercise because NG decided many months ago that no alternative would be selected unless immediately proximate to the pipelines. The search which NG took a year to complete was an endeavour which they did not want to succeed because they were looking for something

they were determined not to find namely a suitable site which is not proximate to those pipelines.

 

You will recall that in September 2006 a report was prepared for your Council in

respect of the previous application submitted by NG which later resulted in the appeal that was dismissed: the recommendation in the Report was that the Council should object to that application "on the grounds of landscape intrusion". The recommendation was approved, the objection submitted and the appeal failed. In view of the issues raised in this letter and the approval of that recommendation I hope that the Council will decide to refuse the present application

 

Yours sincerely,

 

 

 

 

Peter McMurtrie

Chairman

Image
 
© CAPRI 2010